Cut Changeover by Moving Work Outside the Stop

Apply SMED steps to reduce stopped changeover time.

lean-manufacturing5 min read

A press changeover takes 47 minutes of stopped time, causing weekly batches that inflate finished inventory and delay low-volume parts. SMED: observe setup, separate internal from external, convert internal to external, streamline and standardize. The team wants to buy a faster die cart before understanding that much of the stopped time is preparation that should happen before the last good part. Observe Record the full Part A to Part B changeover and list each element: last good part, tool search, crane wait, die removal, cleaning, new die install, first good part. SMED begins with facts. Memory usually underestimates search, walking,…