A print date is threatened, but the team is focusing on visible marketing progress instead of the dependent production chain. Critical Path Method: list activities, durations, and dependencies to find the longest path to the milestone. The common trap is treating the busiest or most visible stream as schedule-critical. A task can be important and still have float if it does not block the ship milestone. List dependent activities Final proof -> legal review -> file correction -> printer upload -> printer preflight. Only include tasks that must happen in sequence for the print milestone. Add durations 2 days +…
Read the full lesson
Sign up free: one personalized lesson every day, matched to your role and goals.
Already have an account? Sign in