A migration has 20 batches. The plan assumed 4 batches per day. After three days, 6 batches are complete, and cleanup appears in every batch. Planned rate -> actual rate -> variance driver -> remaining range -> evidence gate The common shortcut is to keep the original finish date and say the team will catch up. That is not a forecast update unless the catch-up mechanism is real. Capture planned rate Original plan: 20 batches at 4 batches/day = 5 days total. The original plan is the baseline hypothesis, not a promise reality must satisfy. Capture actual rate Actual progress:…
Read the full lesson
Sign up free: one personalized lesson every day, matched to your role and goals.
Already have an account? Sign in