Managing a Tight Project Deadline

Determine if a project can be completed on time

{"problem":"You have a software project with 5 tasks that require these hours to complete: Task A: 10 hours, Task B: 15 hours, Task C: 20 hours, Task D: 5 hours, Task E: 25 hours. The team consists of 3 developers working full-time (40 hours/week). Can this project be completed in 2 weeks?","pitfall":"A novice might underestimate the total hours needed by failing to account for all tasks or overestimating team availability due to distractions or meetings.","steps":[{"label":"Step 1: Calculate Total Hours Needed","calculation":"Total Hours = Task A + Task B + Task C + Task D + Task E\nTotal Hours = 10 +…