Build a Three-Week Make-Ready Plan
Create a three-week make-ready plan from a scheduled construction activity.
Convert the CPM activity Level 3 ceiling close-up into a three-week make-ready plan the field can execute. Last Planner make-ready: scheduled work becomes reliable only when constraints have owners, dates, and evidence of removal. The common shortcut is copying the CPM activity into the weekly plan as if a single bar proves readiness. That hides approvals, inspections, predecessor acceptance, material status, and safe access until crews are mobilized. Step 1 Break the activity into readiness conditions: MEP signoff, firestopping complete, access panels approved, ceiling materials staged, lifts available, and safety access route clear. This converts a vague schedule label into…