Walk the Outage Triage

Prioritize outage work by risk treatment, readiness, and decision ownership.

comparison Outage scope squeeze The kiln outage scope has 126 jobs, 64 hours, and a restart deadline that cannot move. The wrong scope decision can either waste the window or leave the next campaign exposed. Risk treatment triage Risk treated x readiness Every outage job must answer two questions: what risk does it reduce, and is it ready enough to complete without harming the restart? Shortcut Add the loudest request until the window is full. A scope list that protects restart and treats the most material risks. Scope decisions should be transparent enough that people can disagree with the criteria…