Build a Critical Path Move Plan
Create a simple critical path schedule for a constrained moving job.
Plan a same-day pack, load, and delivery with an origin departure target of 1 p.m. and a destination elevator at 3 p.m. Critical Path Method: activities + durations + dependencies = finish-time control Treating every task as equally urgent causes crews to scatter effort instead of protecting the few dependent tasks that determine departure. List activities Kitchen pack: 90 minutes. Furniture wrap: 75 minutes. Elevator load: 120 minutes. Drive: 45 minutes. Destination dock check-in: 15 minutes. A critical path needs named activities and rough durations. Perfect estimates are less useful than visible dependencies. Mark dependencies Furniture cannot load before wrap.…