Build the Release-Day RACI

Create a RACI assignment for a release-day workflow.

before-after score-chip-grid common-trap-callout A release-day checklist has tasks but no decision ownership, causing artwork and metadata fixes to drift. RACI: Responsible does, Accountable owns, Consulted gives input, Informed gets updates The common trap is assigning three accountable people because the task feels important. That creates negotiation at the moment the team needs a decision. List deliverables Write concrete outputs: DSP availability check, metadata correction, social post approval, creator asset delivery. RACI works on deliverables, not vague areas like "release vibes" or "marketing support." Assign Responsible Name the person or role doing the work for each deliverable. Responsible can be more…

Read the full lesson