Sort Civil Risks by Owner and Time Horizon
Classify common civil-project risks by the owner best positioned to manage them.
Place each risk into the owner bucket best positioned to act first. Design lead Field lead Owner or authority External monitor Storm pipe conflicts with proposed footing in the latest model. Excavation sequence may undermine the temporary access road. Permit reviewer has not returned comments before the advertised bid date. Rain forecast may block asphalt placement during the lane-closure window. Retaining-wall detail does not show drainage outlet connection. Utility owner has not confirmed shutdown availability. Spoil pile is being staged too close to the excavation edge. River level forecast may affect cofferdam access next week.