Score A Battery Plant Site Without Hiding The Trade-Offs
Build a weighted decision matrix for EV battery plant site selection and use it to surface trade-offs.
Three possible battery plant sites each have a headline advantage, but the leadership team needs a defensible recommendation. Decision matrix path: criteria, weights, scores, sensitivity, recommendation. The weak move is choosing the site with the largest incentive package. Incentives matter, but they may not offset power readiness, permitting, skilled labor, logistics, or commissioning risk. Before Site A has the best incentives, Site B has labor depth, Site C has lower grid carbon. Leadership is split by function. After Criteria and weights: power readiness 25, commissioning timeline 20, skilled labor 15, logistics 15, incentives 15, carbon and community 10. Site B…