Sort each backlog item by the status it should have before schedule freeze. Ready Blocked Expedite Parked Pump seal replacement with parts staged, permit approved, and handback test defined Fan bearing job scoped, but the required lift is not available until next week Overdue safety relief-valve corrective action with compliance exposure Paint guard rails in an area scheduled for a larger outage next month Conveyor inspection with access window confirmed and no parts required Gearbox replacement missing coupling size confirmation from field walkdown Critical cooling leak that threatens tonight's batch if left running Low-priority label replacement bundled with a future…