Turn the schedule into crew promises
Apply Last Planner conversations to convert a masonry schedule into reliable weekly commitments.
Monday start The GC wants veneer started Monday. Your foreman sees four open constraints: scaffold tag, correct brick blend, window flashing inspection, and a muddy laydown area. The risk is not just delay. Starting before ready creates rework, unsafe workarounds, and broken promises. Last Planner Should -> Can -> Will -> Did -> Learn Do not convert a master schedule line into a crew promise until the constraints are visible and owned. Shortcut Promise Monday because the schedule says Monday. Reliable promises beat optimistic starts. Only promise work that is ready enough to protect safety, quality, and flow. 01 Make-ready…
Sign up free — one personalized lesson every day, matched to your role and goals.
Already have an account? Sign in