Commit to clearing named constraints before a zone or system work package starts.
Run a three-day make-ready constraint sweep before a ship zone, system, or supplier-dependent package starts. Use this for a real shipbuilding moment: cable pulling in a machinery space, pipe spool installation in a ballast tank, accommodation closeout, paint window, class inspection, or vendor commissioning attendance. For [zone/system/package], I will list the top three constraints, name one remover for each, define evidence of clearance, and set a hold point for any constraint not cleared by [date/time]. In 3 days, check whether the constraints were named, owned, and either cleared or converted into a hold point. Before starting cable pulling in a…