Create a deliverable-oriented work breakdown structure for a ship block and avoid action-list planning.
Block 320 is planned as a list of actions: cut, weld, inspect, paint, move, install. The list does not show whether all deliverables are owned once. A WBS should decompose 100% of the scope into deliverables, then attach activities, cost, schedule, and responsibility. The common trap is making the WBS a verb list. Verb lists are useful schedules, but they do not prove scope completeness or prevent duplicate ownership. Before Cut plates; weld frame; install brackets; inspect welds; paint; move to dock. After Block 320 > Structure; Embedded piping; Cable supports; Outfitting foundations; Coating; Lifting and transport; Inspection dossier. 1.…