Plan a Two-Week Sprint Around Dependencies

Sequence Sprint work to retire dependencies and assumptions early.

The Sprint Goal is a working renewal import. UI work can start anytime, but final import depends on customer data mapping. The team assumes the sample file is representative. Plan early validation for path dependencies and RAID assumptions before building dependent work. The common shortcut is to schedule the visible UI first and the data mapping later because the UI is easier to demo. Not quite: if the mapping assumption fails on day eight, the team has burned its adaptation window. Name the Sprint Goal Goal: a renewal import that handles the customer's real file and produces a verified import…