Recall critical path terms and use them in publishing schedule decisions.
comparison battlecard Core term What is the critical path in a publishing schedule? The longest chain of dependent tasks that controls the milestone date. Example: final proof -> legal review -> file correction -> printer upload -> preflight. Float vs delay What is the difference between float and a schedule delay? Do not escalate every slip the same way; first check float. Schedule objection Can we just absorb a two-day author delay? Author approval is before legal review and file upload. Your line We can absorb it only if author approval has at least two days of float. If it…