Robot Commissioning Quick Cards
Recall the core commissioning checks that prevent robot-cell launch gaps.
What is the commissioning question behind every clean auto-cycle demo? Do not stop at motion. Can the plant run, stop, recover, and prove the cell under realistic conditions? A clean cycle is only one slice of readiness. Recovery and evidence decide launch quality. Readiness Can we sign now? The robot already ran ten good cycles. Late SAT pressure after a clean demo. Your line Ten cycles prove motion. Before signoff we still need the safety-state check, one uncoached fault recovery, and the evidence bundle. Agreeing because the visible demo looked successful. It acknowledges the win while naming the missing proof…