Skip to main content

Work Through a Change Order Message

Write a change-order message that explains condition, options, impact, and approval request.

solar-installation-business5 min read

The crew found unexpected hardscape where the original trench scope assumed open soil. Use change control: condition, scope impact, options, approval. The common trap is asking for approval on 'extra cost' without showing the field condition, the original assumption, or the alternatives. That makes the customer debate trust instead of deciding scope. Before 'Concrete issue. Extra trenching cost likely.' After 'Today we found concrete under the planned trench route; the signed scope assumed open soil. Option A saw-cuts and patches the original route for $850 and keeps schedule. Option B reroutes conduit along the fence for $430 but adds one…

Read the full lesson

Sign up free: one personalized lesson every day, matched to your role and goals.

← Back to library

Contact us