Walk the Asset Dependency Triage
Triage asset delays by downstream dependency and available float.
Asset triage Three late assets compete for the same senior artist: creature texture, market-stall prop, rain rig. The right escalation depends on which asset gates the next chain. Critical path Dependency plus zero float equals critical The critical item is the one whose delay delays the project. Prestige, effort, and noise are secondary. Loudest asset first Chases attention instead of schedule consequence. Escalation goes where it protects the delivery chain. Manage the chain of dependency, not the emotional weight of the item. 01 Dependency 02 Float 03 Unblock Find dependency Who waits next
Sign up free — one personalized lesson every day, matched to your role and goals.
Already have an account? Sign in