Zum Hauptinhalt springen

Worked Walkthrough: Price a Scope Variation

Calculate and explain a fee variation for added architecture services.

architecture-practice-management5 min read

A client adds one planning-support workshop, one revised massing study, and a two-page board memo after the Stage 2 fee was agreed. Translate added service into tasks, roles, hours, fee, and assumptions. The common shortcut is to send one rounded number because it feels cleaner. That often backfires: the client cannot see what changed, the team cannot defend the effort, and the next request is easier to treat as included. Name the added service Workshop prep and facilitation, revised massing study, board memo, and principal review. Start with service components, not hours. This keeps the variation attached to the client…

Read the full lesson

Sign up free: one personalized lesson every day, matched to your role and goals.

← Back to library

Kontakt aufnehmen