Zum Hauptinhalt springen

Read Earned Value on a Concrete Package

Calculate basic earned value indicators for a construction work package and interpret the result.

construction-management5 min read

Concrete slab package: budget at completion is $600,000. Planned value is $360,000, actual cost is $420,000, and verified complete work equals 55 percent of budget. Earned Value Management: EV = budgeted value of completed work; SPI = EV / PV; CPI = EV / AC. The common shortcut is reading actual cost or visible crew activity as progress. In construction this can hide poor productivity, out-of-sequence work, or rework because spending can rise faster than earned scope. Step 1 Calculate EV: $600,000 budget at completion x 55 percent verified complete = $330,000 earned value. EV uses budgeted value, not actual…

Read the full lesson

Sign up free: one personalized lesson every day, matched to your role and goals.

← Back to library

Kontakt aufnehmen