Critical Path Producer Deck

Recall critical path terms and apply them to studio schedule decisions.

animation-studio-management4 min read

What is the critical path? The longest dependent chain of work that determines the project finish date. If a task on that chain slips and has no float, delivery slips. What is float in a studio schedule? The amount of delay a shot, asset, or task can absorb before it delays a downstream milestone. Float is recovery room, not permission to ignore the work. Important shot vs. critical shot Compare Many hero shots are important. Only some are critical this week. Objection: The hero shot should always go first. The hero shot should always go first. Supervisor is worried about…