Cabin release is late on turnaround day: at 12:18 p.m., only 61 percent of cabins are marked ready, terminal pressure is increasing, and the existing dashboard is too delayed to guide supervisors. PDCA: Plan the theory, Do a small test, Check side effects, Act on what the data teaches. The common trap is adding more radio pressure to housekeeping without testing where the release actually stalls. Plan Target: reach 85 percent cabin release by 12:45 on two pilot decks. Theory: the delay is caused by hidden inspection and exception queues, not cleaning speed alone. A useful plan includes a prediction.…