Place each battery program activity into the ISO 31000-style risk process bucket. Set context Identify risk Analyze risk Evaluate risk Treat risk Define that the protected objective is March SOP at 20,000 packs per month. Name sodium carbonate allocation as a possible constraint on cathode supply. Estimate the volume shortfall, timing, cost impact, and current supplier controls. Decide whether the remaining launch-volume exposure is acceptable to the steering committee. Add a second-source qualification milestone and inventory buffer. Write the customer approval objective before judging the validation risk. Choose to accept the residual tariff exposure because the contingency reserve covers it.