Sort Planning Signals From Noise

Classify incoming production updates by whether they should change the plan, trigger monitoring, or be filtered out.

production-planning4 min read

Drag each production update into the right action bucket. Change the plan Monitor as a watch signal Filter for now Signed customer order inside the frozen-plus-controlled horizon with approved priority Supplier confirms a two-day delay on a component needed for this week's build Bottleneck machine loses 90 minutes during today's scheduled run Sales hears a retailer may run a promotion next month but has no date or volume yet Demand forecast for a family moves up 6% outside the frozen horizon Procurement says an alternate supplier could qualify in six weeks if needed A manager says the plant feels busy…

Read the full lesson