Skip to main content

Work the Takt Gap

Calculate takt time, compare it to bottleneck cycle time, and choose the correct production-planning lever.

production-planning5 min read

A kit cell must produce 420 kits today. Gross shift time is 540 minutes. Breaks remove 45 minutes, sanitation removes 30 minutes, and the team briefing removes 15 minutes. The bottleneck cycle time is 1.25 minutes per kit. Takt = net available production time divided by customer demand. Compare takt to bottleneck cycle time to see whether the plan pace is feasible. The common shortcut is to compare 420 kits with yesterday's output and tell the team to push harder, without checking the required pace. Net time 540 - 45 - 30 - 15 = 450 net production minutes Use…

Read the full lesson

Sign up free: one personalized lesson every day, matched to your role and goals.

← Back to library

Contact us