Sort Planning Signals From Noise
Classify incoming production updates by whether they should change the plan, trigger monitoring, or be filtered out.
Drag each production update into the right action bucket. Change the plan Monitor as a watch signal Filter for now Signed customer order inside the frozen-plus-controlled horizon with approved priority Supplier confirms a two-day delay on a component needed for this week's build Bottleneck machine loses 90 minutes during today's scheduled run Sales hears a retailer may run a promotion next month but has no date or volume yet Demand forecast for a family moves up 6% outside the frozen horizon Procurement says an alternate supplier could qualify in six weeks if needed A manager says the plant feels busy…
Sign up free — one personalized lesson every day, matched to your role and goals.
Already have an account? Sign in